Equipment delays and supply chain constraints continue to affect project timelines. How are these challenges changing the way data center projects are planned, financed, or delivered?

With the explosion of data center construction, supply chain delays related to cooling units, electrical transformers, generators, and other essential components have become all too common. Owners want predictable pricing, guaranteed completion dates, and maximum risk transfer to keep schedules and costs from spiraling out of control. Contractors are pressing for targeted schedule relief and reasonable caps on liquidated damages to ensure they aren’t left holding the bag when equipment doesn’t arrive on time. Just one break in the chain can trigger cascading disruptions that translate to millions of dollars in claims.

Because these impacts touch every step in the development process, advanced planning is key. Owners are best served purchasing critical long-lead items well in advance, sometimes while design and even financing are still incomplete. This requires a sophisticated understanding of the necessary components and a commitment from lenders to invest in projects earlier than normal. Contractors are experimenting with centralized facilities where complex components are manufactured simultaneously for multiple sites, thus simplifying the chain and reducing exposure to labor shortages.

Stakeholders can successfully manage supply chain constraints at the contracting stage as well. Once relegated to boilerplate force majeure clauses, supply chain risk is now among the most heavily negotiated items in data center agreements. Instead of treating supply chain constraints as unforeseeable, parties identify in advance the likely failure points, define them carefully, and assign responsibility for schedule and cost impacts. Parties also build schedule contingencies and price escalation clauses into their contracts to anticipate supply chain constraints early and leave less room for disagreement if and when the impacts occur.

It’s impossible to avoid supply chain challenges altogether, especially as demand for data centers continues to grow at warp speed. That said, if the risk is embedded in the initial planning, financing, and procurement stages, delays can be mitigated to avoid major scheduling impacts—and costly disputes—down the road.